Search company, investor...

Delta Energy

deltaenergyllc.com

Founded Year

2003

Stage

Acquired | Acquired

About Delta Energy

Delta Energy buys and sells natural gas to industrial consumers in 9 states, and provides energy consulting services for companies that don't want to hire own energy staff. Delta manages energy services for major energy users and is an old-timer in the growing world of energy management, having started nearly 20 years ago.

Headquarters Location

5555 Perimeter Drive

Dublin, Ohio, 43017,

United States

614-339-2600

Missing: Delta Energy's Product Demo & Case Studies

Promote your product offering to tech buyers.

Reach 1000s of buyers who use CB Insights to identify vendors, demo products, and make purchasing decisions.

Missing: Delta Energy's Product & Differentiators

Don’t let your products get skipped. Buyers use our vendor rankings to shortlist companies and drive requests for proposals (RFPs).

Delta Energy Patents

Delta Energy has filed 2 patents.

patents chart

Application Date

Grant Date

Title

Related Topics

Status

8/11/2009

8/20/2013

Carbon forms, Tires, Pigments, Rubber properties, Polymer scientists and engineers

Grant

Application Date

8/11/2009

Grant Date

8/20/2013

Title

Related Topics

Carbon forms, Tires, Pigments, Rubber properties, Polymer scientists and engineers

Status

Grant

Latest Delta Energy News

Best Project, Energy/Industrial: Delta Energy Park

Nov 10, 2022

November 10, 2022 Owner: Lansing Board of Water and Light Lead Design Firm/Structural, Civil and MEP Engineer: Black & Veatch General Contractor: Lansing Power Constructors - Joint Venture Between Barton Malow and Clark Construction Owner's Representative: Kramer Management Site Development: Barton Malow Co. Subcontractors: Hardman Construction; Christman Constructors; Newkirk Electrical Associates; PIC Group; Capital City Erectors; Andy J. Egan Co.; Boiler Tri-Venture; Scheck Mechanical; Motor City Electrical; Patterson Horth Through the development of Delta Energy Park, Lansing Board of Water and Light became the largest utility in Michigan to generate coal-free power by 2025, reducing its carbon emissions by 80%. The new natural gas-fired combined cycle plant is home to three Siemens SGT-800 gas turbines, two Vogt heat recovery steam generators and one Doosan steam turbine. The combustion turbines are each capable of 57 MWs, and the steam turbine generator is capable of 86 MWs. Lansing Power Constructors, a joint venture between Barton Malow and Clark Construction, also delivered a new switch yard and cooling tower. Once complete, Lansing Board of Water and Light was able to retire its Eckert and Erickson coal-fired power stations. With construction beginning in March 2019, the three-year project grappled with the effects of the COVID-19 pandemic. The team had to modify the execution format and timeline in the interest of personnel safety, reducing manpower to limit the risk of exposure. “As a leader that was probably one of the most difficult times of my career,” recalls Craig Lowell, construction director with Barton Malow. “Having a project with that level of complexity on a tight schedule and a tight budget, that was a huge issue.” Adding to the challenge, in November 2020, LBWL requested the project team to evaluate the potential for proving capacity of the three turbine generators months earlier than initially planned. Delivering on this commitment meant that the plant needed to be able to dispatch power to the grid by the end of May 2021 despite pandemic-related setbacks and modifications the team had made to the execution plan. The initial commitment included power generation milestones throughout September 2021. Photo Courtesy of Barton Malow LBWL asked the team to determine achievability, odds of success and assumption of resulting costs to accelerate and realign the schedule. After five days of evaluation, the team determined that it was possible, but the odds of success were not favorable. The modified execution would result in additional costs between $15 million and $20 million. In addition, successful execution would ultimately require contractual methods for key subcontractors to be modified to allow the management team to dictate where and how to apply resources. “We broke everything down into systems,” Lowell says. “How many cables were needed? How many instruments were specifically needed to get just the simple cycle operation down so that we could prove out the simple cycle units? When that was taken care of, we could start working on how we were going to get the combined cycle portion of the plant commissioned and up and running while leaving the simple cycle portion available to be dispatched.” LBWL accepted the plan. Over the next six months, the team successfully reduced the anticipated schedule duration by about five months. The effort included installation of 44,188 linear ft of piping, 1,036 instruments, 775,254 linear ft of cable, 22,483 terminations and the commissioning required to support simple cycle operation. Although the added challenges resulted in the project being behind the original schedule, the team delivered it below the original budget.

Delta Energy Frequently Asked Questions (FAQ)

  • When was Delta Energy founded?

    Delta Energy was founded in 2003.

  • Where is Delta Energy's headquarters?

    Delta Energy's headquarters is located at 5555 Perimeter Drive, Dublin.

  • What is Delta Energy's latest funding round?

    Delta Energy's latest funding round is Acquired.

  • Who are the investors of Delta Energy?

    Investors of Delta Energy include Edison International.

Discover the right solution for your team

The CB Insights tech market intelligence platform analyzes millions of data points on vendors, products, partnerships, and patents to help your team find their next technology solution.

Request a demo

CBI websites generally use certain cookies to enable better interactions with our sites and services. Use of these cookies, which may be stored on your device, permits us to improve and customize your experience. You can read more about your cookie choices at our privacy policy here. By continuing to use this site you are consenting to these choices.